Timetable for council vote on Viking windfarm slips back to July at earliest

Councillors will not vote on the Viking Energy windfarm until July at the earliest due to delays in revising the size and impact of the proposed development.

Viking Energy has admitted that the hotly anticipated alterations it is to make to appease objectors will not now be revealed until the spring rather than “the turn of the new year” as previously hoped.

Viking project coordinator Allan Wishart said the so-called addendum to the environmental impact assessment may only appear in late March or April after which the proposals have to go out to another full round of public consult­ation for at least 28 days. The council has already warned it may seek an extension to that period to allow its own round of consultation before all the new information is eventually gathered and analysed by council planners.

Mr Wishart said Viking hopes for a verdict from councillors at a meeting in early July, which he admitted was a tight schedule, other­wise it may have to wait until after the summer break. Shetland Islands Council had been due to rule on the windfarm on 5th Novem­ber last year before the matter passes to Scottish ministers for a final decision.

When it appears, the addendum is likely to present a smaller wind­farm with fewer turbines and other design alterations in an attempt to respond to objectors and to a large percentage of the Shetland com­munity which feels the proposal is too big for the islands’ landscape.

Mr Wishart said much of the work was going into addressing the objections of statutory bodies includ­ing those from Scottish Natural Heritage and the RSPB about the impact on birds. There has been difficulties in arranging meetings with national bodies and a delay has resulted from the tragic recent death of the main consultant who had done the bird impact assessment work which now needs further work.

Another issue being looked at is Scottish Environment Protection Agency’s concerns about the handling of the mass of peat which would be dug out for the roads and turbines.

Mr Wishart said: “It’s important to get the information all together; get it studied, see what the impact is of the position of turbines, the numbers of turbines – and that is not a simple, straight-forward exercise.”

Meanwhile, Viking has welcom­ed the government’s approval of the £320 million Beauly-Denny power line, without which the Shetland windfarm would not be possible.

As expected, Scottish energy minister Jim Mather announced on Wednesday that Scottish and Southern Energy’s controversial upgrade to the 137-mile spine of large electricity pylons would be permitted, boosting grid capacity from the year 2013 and enabling future onshore and offshore renew­able generators in Shetland, Orkney and the north of Scotland to send their power to the towns and cities in the central belt and beyond.

NO COMMENTS

Add Your Comment

Add Your Comment

Please note, it is the policy of The Shetland Times to publish comments and letters from named individuals only. Both forename and surname are required.

Comments are moderated. Contributors must observe normal standards of decency and tolerance for the opinions of others.

The views expressed are those of contributors and not of The Shetland Times.

The Shetland Times reserves the right to decline or remove any contribution without notice or stating reason.

Comments are limited to 200 words but please email longer articles or letters to editorial@shetlandtimes.co.uk for consideration and include a daytime telephone number and your address. If emailing information in confidence please put "Not for publication" in both the subject line and at the top of the main message.

200 words left

This site uses Akismet to reduce spam. Learn how your comment data is processed.

logo

Get Latest News in Your Inbox

Join the The Shetland Times mailing list to get one daily email update at midday on what's happening in Shetland.